NASA ODAR & EOMP Practice (NASA-STD-8719.14C): Contract Deliverable vs. Regulation

Engineers inspecting a modular satellite bus inside a Pacific Northwest aerospace cleanroom

Primary-source check against NASA-STD-8719.14 and NPR 8715.6B as of 2026-11-16; distinct from Batch 5 status verdict #1963.

ORBITAL SUSTAINABILITY · DISPOSAL REGIME · AGENCY TECHNICAL STANDARD (CONTRACT DELIVERABLE)
NASA ODAR & EOMP Contract Deliverable
Unlike FCC 47 CFR § 25.283(e), NASA-STD-8719.14C and NPR 8715.6B are not federal regulations—they are agency technical standards enforced as binding contract deliverables (ODAR and EOMP) on NASA missions and rideshare payloads.
Primary Authority / Source: NASA ODPO / Standards  |  As-Of / Horizon: NASA-STD-8719.14C & NPR 8715.6B (Active Nov 2026)
ORBITAL SUSTAINABILITY · PDF & MARKDOWN TWIN
NASA ODAR & EOMP Contract Deliverable — Reference Brief
Download the 2-page printable reference PDF or read the clean Markdown twin for AI and briefing workflows.
NASA ODAR & EOMP Deliverable Architecture (NASA-STD-8719.14C)
NASA ODAR & EOMP Deliverable Architecture (NASA-STD-8719.14C)

Documented Instrument & Engineering Record

  • Contract vs. regulation: NASA-STD-8719.14C binds missions through NASA procurement contracts, Space Act Agreements, and launch-integration requirements—not general civil rulemaking.
  • Two required documents: The Orbital Debris Assessment Report (ODAR) is submitted at Preliminary Design Review (PDR) and updated at Critical Design Review (CDR) / Flight Readiness Review (FRR), paired with an End of Mission Plan (EOMP).
  • Standard analytical tools: Mission teams run NASA's Debris Assessment Software (DAS) for orbital lifetime and collision probability, and ORSAT (Object Reentry Survival Analysis Tool) when DAS flags casualty risk near or above 1:10,000.
  • Angle split with Batch 5: Batch 5 Post #1963 confirms NASA ODAR is LIVE; this brief specifies the PDR/CDR deliverable workflow and DAS/ORSAT engineering inputs.

NASA ODAR Deliverable Milestones & Software Gates

Milestone / ArtifactRequirement SourceTechnical Deliverable
Preliminary ODARNPR 8715.6B / PDRInitial orbital lifetime, passivation & casualty estimate
Final ODARNPR 8715.6B / CDR-FRRVerified DAS/ORSAT run with as-built component masses
End of Mission Plan (EOMP)NASA-STD-8719.14CStep-by-step passivation, venting & deorbit execution
Reentry Casualty GateRequirement 4.7-1Total Ec < 0.0001 (1:10,000) across >15 J fragments
Explosion Probability GateRequirement 4.4-1Accidental explosion probability < 0.001

Mission Designer, Compliance Lead & Founder Takeaways

  • WA suppliers building payloads or hosted instruments for NASA missions must supply material/mass breakdowns (titanium, stainless steel, reaction wheels) for ORSAT survivability runs.
  • Contract deliverables cannot be waived by commercial licensing alone; NASA Safety and Mission Assurance (SMA) signs off separately from FCC.
  • Program managers should freeze ODAR component lists before CDR to avoid late-stage demisability redesigns.

Connected Census Profiles, Segments & Rules

Primary Sources & Official Records