Who Owes What by When: Kent, Tukwila, Redmond & Bothell Facilities
WA CBPS applies to commercial and industrial-adjacent buildings over 20,000 sq ft statewide (including Kent Valley and Eastside aerospace campuses). Tier 1 (>50,000 sq ft nonresidential) requires meeting Energy Use Intensity targets (EUIt) or completing an Investment Criteria energy audit, plus establishing an Operations & Maintenance (O&M) program 12 months before the compliance date.
Tier 2 (20,000–50,000 sq ft commercial) requires Energy Management Plans, O&M programs, and ENERGY STAR Portfolio Manager benchmarking by July 1, 2027. Compliance renews every 5 years.
- June 1, 2026: Tier 1 >220,000 sq ft (already passed; active enforcement).
- June 1, 2027: Tier 1 90,001–220,000 sq ft.
- July 1, 2027: Tier 2 20,000–50,000 sq ft.
| CBPS Tier & Size | Compliance Deadline | Core Requirement |
|---|---|---|
| Tier 1 (>220,000 sq ft) | June 1, 2026 | EUIt / Investment Criteria + EMP + O&M |
| Tier 1 (90,001–220,000 sq ft) | June 1, 2027 | EUIt / Investment Criteria + EMP + O&M |
| Tier 2 (20,000–50,000 sq ft) | July 1, 2027 | EMP + O&M + Portfolio Manager benchmarking |
| Tier 1 (50,001–90,000 sq ft) | June 1, 2028 | EUIt / Investment Criteria + EMP + O&M |
Industrial Process-Load Carve-Out & Tenant Data
Aerospace machine shops and cleanrooms can sub-meter industrial process loads (autoclaves, CNCs, vacuum chambers) out of the building's EUIt calculation, but landlords still demand tenant utility and square-footage data.