# WA Clean Buildings Performance Standard (RCW 19.27A.210 / WAC 194-50): LIVE — Tier 1 Live Since Jun 1, 2026

> **Rule:** Washington Clean Buildings Performance Standard (CBPS, RCW 19.27A.200–.240 & WAC 194-50) | **Status:** LIVE | **Instrument:** RCW 19.27A.210 & WA Dept. of Commerce WAC 194-50 | **Date:** June 1, 2026 (Tier 1 >220k) / July 1, 2027 (Tier 2)  
> **Canonical URL:** https://bcesg.org/wa-space-rule-wa-cbps-clean-buildings-live/  
> **Published:** 2026-11-16 · **Program:** FRAME-300-BCESG · **PDF Brief:** https://bcesg.org/wp-content/uploads/2026/11/wa-space-rule-wa-cbps-clean-buildings-live.pdf  
> **Infographic:** https://bcesg.org/wp-content/uploads/2026/11/wa-space-rule-wa-cbps-clean-buildings-live-infographic.png

**Verdict & Proof:** Washington's Clean Buildings Performance Standard (CBPS) is LIVE and in active enforcement. Tier 1 buildings >220,000 sq ft hit their first compliance deadline on June 1, 2026, followed by 90,001–220,000 sq ft on June 1, 2027, Tier 2 (20,000–50,000 sq ft) on July 1, 2027, and 50,001–90,000 sq ft on June 1, 2028.

## Who Owes What by When: Kent, Tukwila, Redmond & Bothell Facilities

WA CBPS applies to commercial and industrial-adjacent buildings over 20,000 sq ft statewide (including Kent Valley and Eastside aerospace campuses). Tier 1 (>50,000 sq ft nonresidential) requires meeting Energy Use Intensity targets (EUIt) or completing an Investment Criteria energy audit, plus establishing an Operations & Maintenance (O&M) program 12 months before the compliance date.

Tier 2 (20,000–50,000 sq ft commercial) requires Energy Management Plans, O&M programs, and ENERGY STAR Portfolio Manager benchmarking by July 1, 2027. Compliance renews every 5 years.

- June 1, 2026: Tier 1 >220,000 sq ft (already passed; active enforcement).
- June 1, 2027: Tier 1 90,001–220,000 sq ft.
- July 1, 2027: Tier 2 20,000–50,000 sq ft.

| CBPS Tier & Size | Compliance Deadline | Core Requirement |
| --- | --- | --- |
| Tier 1 (>220,000 sq ft) | June 1, 2026 | EUIt / Investment Criteria + EMP + O&M |
| Tier 1 (90,001–220,000 sq ft) | June 1, 2027 | EUIt / Investment Criteria + EMP + O&M |
| Tier 2 (20,000–50,000 sq ft) | July 1, 2027 | EMP + O&M + Portfolio Manager benchmarking |
| Tier 1 (50,001–90,000 sq ft) | June 1, 2028 | EUIt / Investment Criteria + EMP + O&M |

## Industrial Process-Load Carve-Out & Tenant Data

Aerospace machine shops and cleanrooms can sub-meter industrial process loads (autoclaves, CNCs, vacuum chambers) out of the building's EUIt calculation, but landlords still demand tenant utility and square-footage data.

## Related BC ESG Guides & Verified Primary Sources

- [BC ESG Anchor: WA CBPS Tier 1 & Tier 2 Guide](https://bcesg.org/washington-clean-buildings-performance-standard-cbps-guide/)
- [Batch 4: WA CBPS & Seattle BEPS Tenant Data](https://bcesg.org/wa-space-ask-wa-cbps-seattle-beps-tenant-data/)
- [Seattle BEPS SMC 22.925 (LIVE)](https://bcesg.org/wa-space-rule-seattle-beps-smc-22-925-live/)
- [WA Dept. of Commerce: Clean Buildings (CBPS)](https://www.commerce.wa.gov/cbps/)
- [RCW 19.27A.210](https://app.leg.wa.gov/RCW/default.aspx?cite=19.27A.210)