Who Owes What by When: ODAR Milestones & 7 Technical Gates
Every commercial contractor building hardware, payloads, or launch vehicles under a NASA contract, Space Act Agreement, or ISS integration order must comply with NPR 8715.6B and format its Orbital Debris Assessment Report (ODAR) under Appendix A of NASA-STD-8719.14C.
Sequential deliverables are tied to mission reviews: a Draft ODAR at Preliminary Design Review (PDR), an updated CDR ODAR typically 45 days before Critical Design Review, and a Final ODAR 30 days before the Safety and Mission Success Review (SMSR).
- Human casualty risk expectation (Ec) on reentry must be < 1 in 10,000 (0.0001).
- End-of-mission passivation (depleting propellant, venting tanks, de-energizing batteries) is mandatory.
- Uses NASA ORDEM orbital debris and MEM meteoroid models; FAA/FCC licenses govern when those agencies hold primary jurisdiction.
| ODAR Gate | Timing | Required Deliverable |
|---|---|---|
| Draft ODAR | PDR | Initial debris, passivation & reentry risk screening |
| CDR ODAR | 45 days prior to CDR | Updated baseline config & nonconformance waivers |
| Final ODAR | 30 days prior to SMSR | Final sign-off package for NASA OSMA / ODPO |
Relevance to Washington Space Operators
Washington firms holding NASA SBIR, CLPS, ISS, or commercial LEO contracts (e.g., Blue Origin, Starfish Space, Gravitics, Portal Space Systems) must flow passivation, demisability, and material-melting data down to component suppliers.