# The 2026–2031 Valley Levee Repair Horizon: Tracking Desimone, Pacific, and Interim Risk

- **Site:** bcesg.org
- **Program:** FRAME-300-BCESG — Freight, Rail & the Valley
- **Pillar:** The Valley
- **Evidence Basis:** Agency Schedule (As-Of 2026-11-16)
- **Primary Agency / Source:** King County DNRP / King County Flood Control District
- **As-Of / Repair Horizon:** 2026-11-16 (Subject to Agency Updates)
- **2-Page Reference PDF:** https://bcesg.org/wp-content/uploads/2026/11/wa-space-valley-levee-repair-timeline-2026-2031.pdf
- **Infographic:** https://bcesg.org/wp-content/uploads/2026/11/wa-space-valley-levee-repair-timeline-2026-2031-infographic.png

> *Repair timelines stated strictly as agencies state them as of 2026-11-16; infrastructure schedules move and must be re-checked.*

## Summary

King County DNRP planning places permanent structural reconstruction of the breached Desimone Levee out toward 2031, while Pacific's White River corridor transitioned into 2026 KCFCD recovery redesign—leaving multi-winter interim exposure.

## Documented Corridor Facts & Continuity Record

- Infrastructure timelines move; as of November 2026, King County DNRP planning documents place full-scale permanent reconstruction of the Desimone Levee out toward 2031.
- The Desimone Levee had already sustained significant damage in 2020 floods before breaching again on December 15, 2025.
- In Pacific, the King County Flood Control District Executive Committee transitioned permanent White River levee replacement into 2026 recovery planning discussions.

## Documented Valley Levee & Corridor Repair Horizons (As of 2026-11-16)

| Project / Reach | Current State | Stated Horizon | Source Agency |
| --- | --- | --- | --- |
| Desimone Levee (Tukwila) | Temporary rock/sandbag plug | Toward 2031 | King County DNRP |
| White River Levee (Pacific) | Emergency reinforcement post-Dec 16 | 2026+ KCFCD planning | KCFCD Exec Committee |
| SR 167 Stage 2a (Pierce) | Under construction | Late 2027 / 2028 | WSDOT Gateway |
| SR 167 Stage 2b (Pierce) | Scheduled 2026–2030 | 2029 open / 2030 wrap | WSDOT Gateway |

## Operational Exposure & Facility Playbook

- Space companies signing 5-year valley leases in 2026–2027 will operate through the entire Desimone 2031 interim repair window.
- Review King County Flood Services project dashboards annually before each October flood season.
- Build the 2031 interim risk window into customer continuity disclosures and property-insurance renewals.

## Connected Valley Cities, Segments & Role Briefs

- [WA Space Cluster Hub (#1382)](https://bcesg.org/washington-space-cluster-census/)
- [Tukwila WA Space Cluster Profile](https://bcesg.org/tukwila-wa-space-cluster-profile/)
- [Kent WA Space Cluster Profile](https://bcesg.org/kent-wa-space-cluster-profile/)
- [Auburn WA Space Cluster Profile](https://bcesg.org/auburn-wa-space-cluster-profile/)
- [Finance: CCA, CBAM & Insurance](https://bcesg.org/wa-space-role-finance-cca-cbam-insurance/)
- [Facilities / EHS Desk Brief](https://bcesg.org/wa-space-role-facilities-ehs-desk-brief/)

## Primary Sources & Agency References

- [King County Flood Services](https://kingcounty.gov/en/dept/dnrp/nature-recreation/environment-ecology-conservation/flood-services)
- [WSDOT Puget Sound Gateway / SR 167](https://wsdot.wa.gov/construction-planning/major-projects/puget-sound-gateway-program)
- [USACE Seattle District (DVIDS)](https://www.dvidshub.net/unit/USACE-SD)