# The 2009 Hanson Dam Seepage Scare: What Actually Happened and the 26-Mile Valley Sandbag Record

- **Site:** bcesg.org
- **Program:** FRAME-300-BCESG — Freight, Rail & the Valley
- **Pillar:** The Valley
- **Evidence Basis:** Historical Event (Corrected)
- **Primary Agency / Source:** USACE Seattle District / King County Flood Control District
- **As-Of / Repair Horizon:** 2026-11-16 (2011–2012 Remediation Complete)
- **2-Page Reference PDF:** https://bcesg.org/wp-content/uploads/2026/11/wa-space-valley-2009-hanson-dam-seepage-sandbagging.pdf
- **Infographic:** https://bcesg.org/wp-content/uploads/2026/11/wa-space-valley-2009-hanson-dam-seepage-sandbagging-infographic.png

> *Primary-source correction: KCFCD funded 26 miles of temporary barriers valley-wide (multi-million-dollar effort including removal), superseding informal '$1.5M / 12 miles in Kent' shorthand.*

## Summary

After a record January 2009 pool revealed right-abutment seepage and sinkholes at Howard A. Hanson Dam, USACE built a grout curtain and drainage system (2009–2012) while King County Flood Control District funded 26 miles of temporary sandbag barriers.

## Documented Corridor Facts & Continuity Record

- Following a record-high pool in January 2009, USACE engineers discovered two sinkholes/depressions and sediment-laden water entering the right-abutment drainage tunnel at Howard A. Hanson Dam.
- While USACE restricted storage and built a subsurface grout curtain (late 2009) plus filtered drains (completed October 2011) and spillway/log-boom upgrades (2012), the valley faced elevated flood odds.
- Primary-source check vs. frame-research shorthand: King County Flood Control District funded 26 miles of temporary industrial sandbag/super-sack barriers across Kent, Auburn, and Tukwila—far exceeding '12 miles / $1.5M in Kent'—with removal alone costing several million dollars.

## 2009 Hanson Dam Seepage: Frame Shorthand vs. Primary-Source Record

| Item | Frame Note | Primary-Source Record | Authority |
| --- | --- | --- | --- |
| Abutment Seepage | 2009 seepage scare | Jan 2009 pool; 2 sinkholes, muddy tunnel flow | USACE Seattle District |
| Temporary Barriers | Kent $1.5M / 12 miles | 26 miles funded valley-wide; multi-$M removal | KCFCD / Local Press |
| Permanent Dam Fix | Not stated in shorthand | 2009 grout curtain; Oct 2011 drains; 2012 upgrades | USACE Seattle District |
| Current Dam Status | 1-in-4 odds (2009 season) | Max pool capacity safely restored post-2012 | USACE Final Safety Studies |

## Operational Exposure & Facility Playbook

- The 2009 episode proves that even before a levee breaches, a dam storage restriction forces valley-wide emergency barriers and multi-year disruption.
- USACE final dam-safety studies confirmed the 2009–2012 abutment remediation reduced risk by an order of magnitude and restored full pool capacity.
- Facilities teams should preserve institutional memory of 2009 staging footprints—knowing which access roads hosted super-sacks prevents dock blockages.

## Connected Valley Cities, Segments & Role Briefs

- [WA Space Cluster Hub (#1382)](https://bcesg.org/washington-space-cluster-census/)
- [Kent WA Space Cluster Profile](https://bcesg.org/kent-wa-space-cluster-profile/)
- [Auburn WA Space Cluster Profile](https://bcesg.org/auburn-wa-space-cluster-profile/)
- [Tukwila WA Space Cluster Profile](https://bcesg.org/tukwila-wa-space-cluster-profile/)
- [Facilities / EHS Desk Brief](https://bcesg.org/wa-space-role-facilities-ehs-desk-brief/)
- [King County Floodplain & Levee Rule](https://bcesg.org/wa-space-rule-king-county-floodplain-levee-live/)

## Primary Sources & Agency References

- [USACE Seattle District (DVIDS)](https://www.dvidshub.net/unit/USACE-SD)
- [King County Flood Services](https://kingcounty.gov/en/dept/dnrp/nature-recreation/environment-ecology-conservation/flood-services)