# SR 167 Completion Project (Puget Sound Gateway): Connecting the Valley to Port of Tacoma by 2029–2030

- **Site:** bcesg.org
- **Program:** FRAME-300-BCESG — Freight, Rail & the Valley
- **Pillar:** The Corridors
- **Evidence Basis:** Agency Schedule (As-Of 2026-11-16)
- **Primary Agency / Source:** WSDOT Puget Sound Gateway Program
- **As-Of / Repair Horizon:** 2026-11-16 (Target 2029–2030)
- **2-Page Reference PDF:** https://bcesg.org/wp-content/uploads/2026/11/wa-space-corridor-sr-167-completion-port-tacoma.pdf
- **Infographic:** https://bcesg.org/wp-content/uploads/2026/11/wa-space-corridor-sr-167-completion-port-tacoma-infographic.png

> *Construction stages and target opening dates stated strictly per WSDOT Puget Sound Gateway Program as of 2026-11-16.*

## Summary

WSDOT's SR 167 Completion Project builds a 6-mile tolled expressway linking Puyallup to I-5/SR 509 near the Port of Tacoma, with Stage 1a and the first 2 Port-to-I-5 miles open and Stage 2b running through 2029–2030.

## Documented Corridor Facts & Continuity Record

- The SR 167 Completion Project closes the missing 6-mile freight gap between Puyallup (existing SR 167) and I-5/SR 509 near the Port of Tacoma.
- Stage 1a (70th Ave East Bridge over I-5 in Fife) is complete, and the first 2 miles between I-5 and SR 509 near the Port of Tacoma are open.
- Stage 2a (SR 161 to SR 410, including a diverging diamond interchange) is in progress for late 2027 opening (finishing 2028); Stage 2b (I-5 to SR 161) is scheduled 2026–2030 with 2029 opening.

## WSDOT SR 167 Completion Project Phasing

| Stage | Scope | Status / Target | Freight Impact |
| --- | --- | --- | --- |
| Stage 1a | 70th Ave E Bridge over I-5 (Fife) | Complete | Improved I-5 port access |
| Port-to-I-5 Segment | 2 miles I-5 to SR 509 / 54th Ave E | Open | Direct Port of Tacoma link |
| Stage 2a | SR 161 to SR 410 widening + DDI | 2025–2028 (Open late 2027) | Removes Puyallup bottleneck |
| Stage 2b | I-5 to SR 161 new expressway | 2026–2030 (Open 2029) | Completes valley-to-port link |

## Operational Exposure & Facility Playbook

- Until Stage 2b opens in 2029, Tacoma breakbulk and container drayage from Kent/Auburn still funnel through congested I-5/Fife interchanges.
- Factor active 2026–2029 construction detours and lane closures around Fife/Puyallup into heavy-haul OSOW permit routing.
- Once complete, Stage 2b gives Green River Valley space manufacturers a direct expressway corridor to Tacoma's East Blair 1 / Terminal 7 breakbulk berths.

## Connected Valley Cities, Segments & Role Briefs

- [WA Space Cluster Hub (#1382)](https://bcesg.org/washington-space-cluster-census/)
- [Auburn WA Space Cluster Profile](https://bcesg.org/auburn-wa-space-cluster-profile/)
- [Kent WA Space Cluster Profile](https://bcesg.org/kent-wa-space-cluster-profile/)
- [Supply-Chain & Procurement Desk Brief](https://bcesg.org/wa-space-role-procurement-lead-desk-brief/)
- [Launch Segment Continuity Exposure](https://bcesg.org/wa-space-launch-continuity-corridor-exposure/)

## Primary Sources & Agency References

- [WSDOT Puget Sound Gateway / SR 167](https://wsdot.wa.gov/construction-planning/major-projects/puget-sound-gateway-program)
- [NWSA Terminals & Breakbulk Operations](https://www.nwseaportalliance.com/cargo-operations/terminals)
- [WSDOT Commercial Vehicles & OSOW](https://wsdot.wa.gov/travel/commercial-vehicles)